Thursday, February 2, 2023

 2-1-2023

Interior finishing has been labor intensive.   We have installed approximately 2,200 lineal feet of 1x8 tongue and groove pine boards.   They have been stained and 2 coats of polyurethane applied.  All of the ceilings - either t&g boards or barnwood, have been installed.   The headboard design in the master bedroom is nearing completion.  All of the stairway openings are mostly complete, including stairway lighting.    The bedroom on the second floor has sheetrock on the walls and the toilet area - tucked under the curved stairway on the 3rd floor is nearing completion - barnwood on the ceiling and walls.










No comments:

Post a Comment

 We are nearing completion.   Open House is scheduled for Sunday, July 23, 2-5 Finish work has been slow and tedious.    The outside patio a...