Finally made it to the top. The interior walls are up to the top of the silo. Heat chased us out of the silo. Early tomorrow we will cut the metal rods sticking up at the top and then back to working on the octagon roof. I had a crane scheduled for Thursday, but I do not think we will have it ready. My grandson's Jack and Carrter are peaking of the top at 45' up
Monday, July 18, 2022
Subscribe to:
Post Comments (Atom)
We are nearing completion. Open House is scheduled for Sunday, July 23, 2-5 Finish work has been slow and tedious. The outside patio a...
-
We are nearing completion. Open House is scheduled for Sunday, July 23, 2-5 Finish work has been slow and tedious. The outside patio a...
-
11-04-2022 Progress is slow at the silo. We have visitors almost continually at the cabin. The HVAC is now completed! We will have a 5 ...
-
6-12-2023 It has been 6 weeks since my last post. We have constructed a sheltered/patio area. Progress continues on this phase. We hav...